2011 budget Acquisition Reform Aegis AEHF Afghan surge Afghanistan AgustaWestland airborne laser Airbus Al Qaeda Allies Alternate Engine Al-Yamamah American Enterprise Institute Ammunition Industrial Base APL Arms Control Arms Sales Arms Transfers Army Arrow Ashton Carter Babcock & Wilcox BAE Systems Bath Iron Works Bechtel BMDR Boeing Brown C-17 C-2 CAPE Carriers CENTCOM CH-47 Chabraja China climate change Cluster Bombs Cluster Munitions Conflicts of Interest Constellation CVN-78 CVN-91 cyber attack cyber defense cyber offense Cyber Threats Cyber Warfare DDG-1000 DDG-51 defense acquisitions Defense Budget Defense Business Board Defense Industry Defense Planning Defense Spending deficit Democrats & Defense deterrence Donald Rumsfeld Dong Feng DRS Technologies EA-18G EADS Efficiency Initiative EFV EH101 energy security Expeditionary Fighting Vehicle Export Controls F-16 F-22 F-35 Finmeccanica FMS FMTV force structure forcible entry Ford class Foreign Military Sales Free Trade Future Combat Systems GBI GCV General Dynamics General Mattis General McChrystal Global Hawk Global Strike GMR Greyhound Ground Combat Vehicle guns versus butter Handheld Manpack Radio Hapag-Looyd Helicopters Heritage Foundation High-Speed Rail Homeland Security Humvee hybrid warfare ICBM Inherently Governmental insourcing Intellectual Property Intelligence Community Iran Iran Sanctions Iraq Israel Jammer JFCOM Joint Forces Command Joint Heavy Lift Joint Operating Environment Joint Stars Joint Strike Fighter JSTARS JTRS KC-45 KC-X Kent Kresa Korea Larry Prior Linda Hudson Littoral Combat Ship Lockheed Martin Logistics Lynn M1 Mabus Maersk ManTech manufacturing Marine Corps Marine One Marinette Massachusetts M-ATV MH-60 Mid-term election Mine Countermeasures Mine Warfare Missile Defense MQ-9 MRAP NASA National Security Strategy NATO Navy NCADE Network-Centric Warfare Next Generation Jammer NGEN Nigeria NII Nimitz class NLOS-LS NMCI Non-Proliferation Norm Dicks North Korea Northrop Grumman NPR Nuclear Power Nuclear Shipbuilding Nuclear strategy Nuclear weapons Nunn-McCurdy O&M Operations and Maintenance Oshkosh Osprey P-8 Partnering Patriot PBL Performance-Based Logistics Persian Gulf Phalanx presidential helicopter Private Contractors Public-Private Partnerships QDR QHSR Rapid Fielding Initiative Ray Mabus Raytheon Rebalancing Reset RIMPAC Robert Gates Rocket Motors Ron Epstein RQ-7 Russia S-300 Samsung SBINet Scan Eagle Secretary Gates Shadow shipbuilding Sikorsky Soft Power solid rocket motor South Korea Space Tracking and Surveillance Satellite Space-X SSBN SSBN(X) Standard Missile Standard Missile 3 START Treaty Strategic Architecture strategic arms control Submarines Super Hornet Sustainable Defense Sustainment Taiwan Taliban Tanker terror terrorism THAAD Trade Deficit Trade Policy Trident Trident submarine UH-60 Unmanned Aerial Systems Unmanned Aerial Vehicles US Ports US101 USS Missouri V-22 Vertical Lift Virginia class weapons spending Wes Bush WGS Wideband Global Satcom William Perry World Trade Organization WTO Yemen
Recent
<< Previous
Next >>

F-35 Alternate Engine Problems Delay Deliveries, Drive Up Costs


Andrea Shalal-Esa of Reuters reported this week that deliveries of the alternate engine being developed by General Electric and Rolls Royce for the F-35 joint strike fighter will be delayed by a year. Repeated testing failures are forcing the engine team to redesign an important part, driving up costs for the huge fighter program while putting off the time when users can benefit from competition between the GE-Rolls engine and the primary engine built by the Pratt & Whitney unit of United Technologies.

The problems with the alternate engine appear to be more serious than difficulties that cropped up in developing the Pratt engine several years ago. GE and Rolls can no longer hold to their baseline schedule, and are being forced to replan their entire development and production program. According to a senior government official conversant with the troubles, plans to compete the primary and alternate engines have slipped by a year, and now will not be fully implemented until the production lot delivered in 2016.

The Obama Administration has argued since entering office that the alternate engine is a waste of money that will drive up the costs of building the F-35 for three U.S. services and nine overseas allies. Because cost is a critical determinant of whether allies remain engaged on the program, the problems GE and Rolls are encountering reach far beyond the fate of a single engine. They also underscore a point made by Senator Tom Harkin during debate about whether to fund the alternate engine: having two redundant engines increases the complexity of the program, potentially undercutting both affordability and readiness.

Loren B. Thompson, Ph.D.

Return to Early Warning Blog
<< Previous
Next >>
1600 Wilson Boulevard, Suite 900
Arlington, VA 22209
P: 703-522-5828 | F: 703-522-5837
©2009 Lexington Institute. All Rights Reserved.
Website designed by Borcz:Dixon | Powered by Agency of Record